Click here for the latest project update sent November 25, 2019.
This project will construct a critical segment of the Red Electric Trail system, a pedestrian and bicycle bridge between Beaverton-Hillsdale Highway and SW Capitol Highway. This trail segment will include a 10-foot wide trail from the intersection of SW Bertha Boulevard and Beaverton-Hillsdale Highway, travelling south over a ravine on a 14-foot wide bridge, where it will intersect with SW Capitol Highway.
Additional project elements include:
· Retaining walls
· Lighting
· Guardrail work along Beaverton-Hillsdale Highway
· Sidewalk curb ramps
· Pedestrian and bicycle crosswalk striping
· Grading and drainage
· Vegetated stormwater facility
· Tree mitigation plantings
· Restoration plantings
The design phase of this project is scheduled to wrap up in spring of 2020 and construction is proposed to begin in late 2020.